White 110mm PVC waste pipe clipped along a rendered wall and around a concrete balcony slab on a Plattekloof first-floor addition

Project · Plattekloof, Northern Suburbs

First-Floor Addition Plumbing | Plattekloof Project Rough-In

A first-floor addition in Plattekloof needed its new waste taken out of the building, around a concrete balcony slab, down the wall and into a new underground drain. These photos show the work at rough-in, before testing, backfill and sign-off.

The challenge

Draining a new upper floor on an existing house

Adding a bathroom or kitchen upstairs means the waste has to get from the first floor to the sewer with enough fall, without blocking, and without letting drain smells back into the house. On this Plattekloof home the route ran outside the building: a high-level run along the wall, an offset around the balcony slab, a vertical stack with a vent, and a new underground line joining the existing drain.

For an addition in Plattekloof or nearby Welgemoed and Panorama, the useful starting point is your own building plan: fixture positions, slab projections and the existing drain determine whether a similar external route is practical.

On site

The installation in three stages

From the first-floor outlet down to the underground connection, photographed at rough-in.

White 110mm PVC waste pipe clipped along a rendered wall and around a concrete balcony slab on a Plattekloof first-floor addition
Upper waste run clipped to the wall and taken around the balcony slab before dropping down the elevation.
Scaffold and offset bends routing a PVC waste pipe around a first-floor concrete overhang in Plattekloof, Cape Town
Working off scaffold to set the offset bends around the overhang and line the pipe up with the drop below.

01 · Upper run

Horizontal high-level routing and the balcony offset

The new first-floor fixtures connect to a white 110mm PVC waste pipe that leaves the building at upper level and runs along the rendered wall. Saddle clips support the run along its route. Drainage needs a suitable continuous fall; the photographs do not verify the measured gradient or support spacing, which must be checked on site before sign-off.

Where the concrete balcony slab projects out from the wall, the pipe is taken around the overhang with angled bends rather than tight 90-degree elbows. Gentler changes of direction keep the flow smooth and leave fewer places for solids to catch. This part of the job was set out working off scaffold so the upper line could be aligned with the vertical drop below.

Double-storey vertical PVC waste stack and vent pipe rising past upper windows on a Plattekloof home
Vertical stack running between the window openings, with the vent pipe continuing upward.

02 · Vertical stack

Vertical stack alignment and continuous venting

From the upper run the waste drops down the elevation as a vertical stack, routed between the window openings so it stays clear of frames and reveals and remains accessible on the outside of the house.

The stack continues upward as a vent pipe above the upper windows. Venting lets air into the system as water falls, so the suction a rushing stack creates cannot pull the water seal out of the toilet, basin and shower traps inside. Vent termination positions are governed by SANS 10400-P and the openings around them, and are confirmed for each house.

Base of a white PVC soil stack turning into beige underground drain pipe in an open trench in Plattekloof
Base of the stack: the white above-ground pipe turns into the beige underground drain line in the trench.
Beige underground PVC drain with an angled Y-junction and capped access point in an open trench beside a Plattekloof house
Underground line joined with an angled junction, with a capped access point left for future rodding.

03 · Below ground

Sub-surface trenching and the main connection

At the base of the stack, the white above-ground pipe turns through a bend into beige pipe laid in an open trench. Pipe intended for burial must be suitable for the ground conditions and loading. Colour alone does not establish a pipe's rating; product markings, bedding and protection need to be checked before backfilling.

The new line joins the existing drainage with an angled Y-junction (slant tee), so the branch flow enters in the direction of travel instead of colliding with it at a right angle. A capped access point is left at ground level so the line can be rodded or jetted in future without digging.

Honest note: the products installed, final measurements, gradients and connection methods on any project depend on that site's layout, existing drainage and the approved plans. Figures above describe this type of installation; they are not a specification for your home.

Building up and not sure where the drains will go?

Send us your plans or a few photos of the wall and existing drain. We'll tell you what to plan for before the builder closes anything up.

Standards

Standards to check before final sign-off

Plain-language summary. The standards themselves set the exact figures; your plumber applies them to your site.

Standard / topicWhat it requiresOn this Plattekloof job
SANS 10252-2 — falls on horizontal drainsDrainage pipes laid to a suitable continuous fall.Upper 110mm run supported along the wall; measured fall remains an on-site verification item.
SANS 10252-2 — pipe supportPipes supported at intervals that prevent sagging and movement.Saddle clips fixed along the horizontal run and down the vertical stack.
SANS 10400-P — ventingVenting arranged to protect trap seals, with suitable termination clearances.Vent shown continuing up the outside wall; final height and clearances require inspection.
Underground drainage — pipe & beddingPipe rated for burial, laid on suitable bedding and protected before backfilling.Beige pipe shown in an open trench; rating, bedding and testing must be verified before backfill.
Access for maintenanceAccess points provided so drains can be cleared without excavation.Capped ground-level access point left at the junction for future rodding or jetting.

For homeowners, builders & architects

Four things to get right on an addition

01

Bring the plumber in at design stage

Decide where waste pipes will leave the first floor before slabs are cast and walls are closed. Sleeves and routes planned early avoid core-drilling cured concrete and awkward offsets later.

02

Use the right pipe for where it lives

Above-ground PVC on a sunny Cape Town wall should be a solvent-weld product suited to outdoor exposure, and it is often painted to match the house. Below ground, use pipe rated for burial — not offcuts of above-ground waste pipe.

03

Leave access before you backfill

Rodding and inspection points are cheap to add while the trench is open and expensive to add after paving. Ask where they will be before the ground is closed.

04

Test before anything is hidden

Concealed and underground pipework should be tested while it can still be seen. Agree the testing step with your builder so it happens before backfilling and plastering.

How we work on additions

  1. Assessment

    We look at your plans or the site, the new fixtures and where your existing drain runs.

  2. Written quote

    A written fixed quote before work starts. Nothing chargeable goes ahead without your approval.

  3. Rough-in & connection

    Pipework installed to the relevant SANS standards in step with your builder.

  4. Test, sign off & guarantee

    COC issued where required after testing, plus our 12-month workmanship guarantee.

Questions about first-floor drainage

Often, yes. On this Plattekloof addition the new first-floor waste was taken out through the wall and run on the outside of the building instead of being channelled through finished ground-floor rooms. The pipe travels along the upper wall with a steady fall, is taken around the concrete balcony slab with angled bends, then drops down the elevation as a vertical stack into a new underground line. Whether an external route works for your home depends on where the new fixtures sit, the wall construction, the position of your existing drain and how the route will look once the building is finished. We look at those points on site and explain the options before quoting, so you know what will be inside and what will be on the outside of the house.

Waste water and solids flow more smoothly around gradual changes of direction. A sharp 90-degree elbow on a drain run creates turbulence, slows the flow and gives solids a place to catch, which is how many recurring blockages start. On this project the upper run was taken around the balcony overhang with angled bends, and the underground branch was joined into the main line with an angled junction rather than a square tee. The exact fittings used on any job depend on the space available, the pipe sizes and the direction of flow, and we choose them on site with the relevant drainage standard in mind. If you are planning an addition, leaving room for these gentler bends in the design is far easier than trying to fit them in after the walls and slabs are built.

When water rushes down a vertical stack, it can pull air behind it and create suction in the pipework. Without a way for air to enter, that suction can drain the water seal from toilet, basin and shower traps inside the house, and once a trap is empty, drain smells can come into the room. A vent pipe extending upward from the stack lets air in and out so the pressure in the system stays balanced and the traps keep their seal. On this Plattekloof addition the vent continues up the outside wall above the upper windows. Where and how high a vent ends is set by the building regulations and the layout of the roof, windows and openings around it, so it is planned for each house rather than copied from another job.

Yes, where the work requires one, but only once it is finished, tested and inspected. The photos on this page show the Plattekloof job at rough-in stage, so the Certificate of Compliance is still pending final inspection, testing and sign-off. We do not describe a certificate as issued before that happens. If you are building, ask your plumber when testing will happen relative to backfilling trenches and closing walls, because underground and concealed pipework should be checked while it can still be seen. You will receive a written fixed quote after an on-site assessment that sets out the scope, and no chargeable work starts until you approve it.

Plattekloof · Welgemoed · Panorama · Parow North

Planning an addition in Plattekloof or the Northern Suburbs?

Tell us the intended fixtures and the stage of your building work. We'll assess on site and confirm a written fixed quote before anything starts.

Quick enquiry